Kidston pumped hydro to have more storage

Kidston pumped hydro to have more storage

genex
Genex TFS Opimisation General Arrangement

In an ASX announcement Genex Power reported on its Technical Feasibility Optimisation which upgrades the storage from 6 to 8 hours operation at 250 MW.  This is an additional 33% over the earlier indications that it would provide 6 hours operation at 250 MW.

Other conclusions from the optimisation are that variable speed pump-turbines will provide a better outcome than the originally proposed fixed speed pump-turbines, and that the upper reservoir can be provided by using the existing Wises pit rather than the proposed turkey’s nest dam.  Utilising the existing pit will reduce capital cost.

Modelling by Mott MacDonald showed that by using variable speed pump-turbines the start up time can be reduced to less than 30 seconds.

The TFS optimisation concluded that the project cost, including contingency, is about $330million. The project also requires the construction of a 275 kV transmission line to connect to the existing infrastructure at Mt Fox.

Full details of the announcement is available at Genex

 

Snowy Hydro has a better solution than batteries

Snowy Hydro has a better solution than batteries

Talbingo dam above Tumut 3 pumped hydro power station

Snowy Hydro boss Paul Broad has been out and about talking up the merits of pumped hydro over chemical battery storage such as the much touted Tesla installation in South Australia.  According to AFR, Snowy Hydro has been crunching the numbers and reveals that the cost of Snowy 2.0 and transmission lines would add $127 per year to the average household electricity bill by 2027.  Snowy Hydro says that providing the same storage using batteries would add a staggering $4000.00 per year to the average bill.

Its hard to believe that such numbers could be true.

The shear magnitude of the snowy 2.0 project gives some credibility to the notion that pumped hydro could be cheaper for large storage.  A characteristic of pumped hydro is that the magnitude of energy stored is related to the water volume, and for a given power station size, the water volume can often be increased at low marginal cost, and so per megawatt-hour the cost can fall dramatically.  In the case of the Cultana project costed at about 1/3 the cost of equivalent batteries for the same energy storage, the storage component could be increased by increasing the size of the upper turkeys nest dam.  The dam cost portion of the project is quite low at less than 10% of project cost.  This chart taken from the Cultana Knowledge Sharing Report shows that increasing hours of storage has a low impact on overall project cost and shows significant reduction in cost per unit of storage.

Storage costs of Cultana project
Storage costs of Cultana project

In the case of the Snowy Hydro project, because the dams to be used, Talbingo and Tantangara, are both existing the storage element of the project is already provided, and the costs will vary with the nameplate capacity of the project.  And because the dams can store an enormous amount of energy, the per unit costs is expected to be quite low.

Snowy Hydro is not releasing much detail about the project, but based on rudimentary information about the elevation difference between the two dams and a generating efficiency of around 85% the energy storage potential can be estimated. Tantangara stores 254 gigalitres which is 87 times larger than the Cultana project.  Talbingo stores 920 megalitres of water and is about 600m below Tantanagara — this 600m of head is more than double that available at Cultana. Assuming that only half the capacity of the smaller of the two dams is available for the pumped hydro operation, that is about 43 times more volume and double the head for about 80 times the energy available at Cultana.  Cultana stores about 1.7 gigawatt-hours of energy, and that would suggest Snowy 2.0 can store about 136 gigawatt hours of energy.

Compare this to the entire world’s production of lithium batteries of about 35 gigawatt-hours per annum — this would mean that to provide the same storage capacity in lithium batteries would require the next 4 years world production of lithium batteries to be dedicated solely to this project (or assuming Tesla’s new battery gigifactory does come on line fully by next year, it may mean about three year’s production.)  Its clearly not credible that batteries could offer a high penetration of grid scale storage any time soon and gives credence to the idea that large scale storage is better provided by pumped hydro than batteries.

The idea that batteries could ever add $4000 to the average electricity bill though is quite bizarre. For small scale storage batteries have a clear advantage and can be deployed very quickly.  When used behind the meter they are already economical and any tendency for power prices to rise will encourage the use of storage in this manner, and so the possibility of prices rising to the stratospheric levels suggested by Broad is implausible.

You can read the full Snowy Hydro story in AFR here.

Study finds Cultana seawater pumped hydro project feasible

Study finds Cultana seawater pumped hydro project feasible

Cultana - www.abc.net.au
Cultana area Spencer Gulf

A consortium of EnergyAustralia, Arup and The University of Melbourne’s Energy Institute (MEI), with funding assistance from ARENA, has undertaken a feasibility study for a seawater pumped hydro project in South Australia’s Spencer Gulf. The study found that the the project is technically feasible with a capital cost of just over $2.1 million per MW of capacity and $270 per kWh of storage. This is towards the high side for pumped hydro projects due to relatively long penstocks and the significant structures to exchange water with Spencer Gulf.

Full details of the study can be found here in the form a knowledge sharing report.

Pumped hydro in China exceeds entire Australian coal power capacity.

Pumped hydro in China exceeds entire Australian coal power capacity.

Existing pumped hydro in China as at end of 2016 amounts to 26 Gigawatts compared to entire Australian installed coal capacity of 22 Gigawatts.

According to Qian Ganglian of China Renewable Energy Institute, at the end of 2016, the Hebei Fengning Pumped Storage Power Station (3,600MW) is the largest pumped storage power station under construction. The Guangdong Guangzhou Pumped Storage Power Station (2,400MW) and Guangdong Huizhou 1 Pumped Storage Power Station (2,400MW) respectively boast the largest installed capacity currently in operation. The station with the largest pump-turbine under construction is Guangdong Yangjiang Pumped Storage Power Station (400MW). The Zhejiang Xianju Pumped Storage Power Station (375MW) boasts the largest pump-turbine currently in operation. Zhejiang Changlongshan Pumped Storage Power Station has the highest head under construction with rated head of 710m, while the operational Shanxi Xilongchi Pumped Storage Power Station has a rated head of 624m).

While we vacillate over energy storage in Australia, China is surging ahead with construction of pumped hydro projects. Just counting pumped hydro projects under construction in 2016 their capacity exceeds the entire installed capacity of fossil fuel power stations in Australia.  As at end of 2016 there are 26 pumped hydro installations under construction and amounting to a capacity of 32 GW. In Australia fossil fuel generators account for 32 GW made up of Coal 22 GW, OCGT 6 GW, CCGT 2 GW, and other Gas 2GW

China has embraced the need of storage in the network and clearly recognises the value of pumped hydro in a network with increasing penetration of renewable generation. The value proposition for pumped hydro is partly related to the long transmission lines from the wind and solar energy rich areas of the north west to the high demand areas of central and east china.  In this respect the long transmission lines are reflective of Australia’s long thin network.  Pumped hydro acts to flatten the peaky output of both wind and solar and make better use of, or postpone or eliminate transmission augmentation. In this way it can be considered a transmission asset rather than a generation asset and recognition of the value of this role will need some market adjustment in Australia.

Being a largely state owned electricity grid makes it easier to make decisions beneficial to the grid at large. Pumped hydro can reduce the overall cost of generation/transmission and in the past when our electricity generation and distribution were government owned, pumped hydro projects such as Tumut 3, Wivenhoe and Sholhaven were built. Yet in a market such as the NEM its not clear how it can reward pumped pumped hydro (or any storage) adequately as a commercial enterprise.

We see some progress now with the announcement of the Snowy Hydro 2 pumped hydro project and yet the feasibility study is being done by political decree and it will be interesting to see how the numbers stack up. AEMO proposed changes to the 5 minute rule for bidding and settlement may also help the numbers stack up.

ANU identifies 185 pumped hydro sites in SA

ANU identifies 185 pumped hydro sites in SA

Research from The Australian National University has identified 185 potential sites for pumped storage hydro installations in  South Australia.

South Australia is the state with the largest proportion of variable renewable electricity (wind and solar PV). This is expected to increase into the 50% to 100% range in the coming years.

The sites are published in the South Australian Pumped Hydro Atlas.

In light of Chief Scientist Dr Alan Finkel’s final report on the review of the electricity market’s security, Professor Andrew Blakers said the new findings provided a valuable contribution to the national discussion on energy security.

“Our work shows that there are many sites in South Australia that may be suitable for establishing pumped hydro storage, to help build a sustainable, secure and affordable electricity grid,” said Professor Blakers, the study’s lead researcher from the ANU Research School of Engineering.

“This assessment is based on very appealing physical characteristics, but the 185 potential upper reservoir sites identified would require detailed due diligence involving land ownership, engineering, hydrological, environmental and other considerations.”

The Australian Renewable Energy Agency (ARENA) is providing $449,000 support for an ANU-led feasibility study, aiming to develop a nation-wide atlas of potential off-river pumped hydro storage sites.

Switzerland doubles capacity of Veytaux pumped storage power station

Switzerland doubles capacity of Veytaux pumped storage power station

Last week, Forces Motrices Hongrin-Léman SA officially inaugurated Switzerland’s second most powerful pumped storage power station in Veytaux. With the FMHL+ project the capacity of the Veytaux pumped storage power station will be increased from 240 MW to 480 MW, with 60 MW acting as a reserve.  To achieve this, two machine groups with 120 MW capacity each have been installed in a new cavern that has been constructed since 7 April 2011.

The pumped storage power station Veytaux will play a crucial role in supplying electricity to the French-speaking part of Switzerland. The project is the response to the increasing demand for balancing energy, which has been triggered by the rapid development of the new renewable energies that generate energy in an intermittent and fluctuating manner.

General layout of Veytaux power station

The existing power station consists of four 60 MW pelton turbines and the new additional capacity will be provided by two 120 MW generating units. The power station operates with a head of 800m from upper reservoir of Hongrin and is discharged into, and pumped from Lake Geneva.

They new units were constructed in an impressive cavern that is 100 m long, 25 m wide and 56 m high, and are controlled remotely by Alpiq’s Centre d’Exploitation et de Gestion de la Production in Lausanne. The construction work was carried out without major incidents and within budget. Veytaux pumped storage power station is Switzerland’s second most powerful behind the Linth-Limmern facility in the canton of Glarus.

The CHF 331 million invested by the FMHL partners – Romande Energie (41.14%), Alpiq (39.29%), Groupe E (13.14%) and the City of Lausanne (6.43%) – demonstrate their long-term vision within an energy context that is not very favourable for hydropower. The low wholesale prices on the European power market do not reflect the value of hydroelectric energy nor the essential role played by pumped storage power stations for the security of supply. Pumped storage power stations provide control energy that is indispensable for the balancing of the electricity grid and are currently the most efficient way of storing vast quantities of electricity and feeding them back into the grid when demand is high. Pumped storage power stations are essential in order to ensure the stability of the Swiss and European electricity grid in view of the rapid development of wind and solar energies.

Turnbull proposes new pumped hydro for Tassie

Turnbull proposes new pumped hydro for Tassie

Already rich in hydro, pumped storage can make better use of available resources, with Tasmania hoping to become the renewable energy battery for Australia. Prime Minister Turnbull announced plans to expand existing hydro capacity and add the possibilty of 2500 MW of pumped hydro.

ARENA will examine four large projects: Mersey Forth-1, Mersey Forth-2, Great Lake and Lake Burbury – with capacity of around 500-700 MW each – and an alternative of nine small scale sites totalling 500MW.

Turnbull says pumped hydro can further stabilise the National Electricity Market and underpin additional wind investment in the State.

This announcement also refers to the study by Dr John Tamblyn on the case for a second interconnector to the mainland. Dr Tamblyn’s report finds another interconnector might be beneficial, but will depend on the ongoing development of the electricity system in Tasmania and the National Electricity Market.

See full transcript of press conference at Trevallyn here.

US sub-committee proposal to increase pumped storage opportunities

US sub-committee proposal to increase pumped storage opportunities

A bill entitled the Bureau of Reclamation Pumped Storage Hydropower Development Act was heard by a US legislative sub-committee last week.  If approved this bill could stimulate non-federal development of pumped storage hydropower using reservoirs under the control of the Bureau of Reclamation in the 17 western states.
This bill would amend the 1939 Reclamation Project Act to remove ambiguity by making it clear that pumped hydro using multiple reservoirs is encouraged.  This would empower state, local and regional leaders to develop pumped hydro projects using reservoirs under federal control.
The US Bureau of Reclamation was established in 1902 and is best known for the dams, powerplants, and canals it constructed in the 17 western states. These water projects led to homesteading and promoted the economic development of the West. Reclamation has constructed more than 600 dams and reservoirs including Hoover Dam on the Colorado River and Grand Coulee on the Columbia River.
Reclamation is the second largest producer of hydroelectric power in the United States. Their 53 powerplants annually provide more than 40,000 gigawatt hours of electricity. This is almost enough to power the entire state of Queensland which has an annual demand of around 50,000 gigawatthrs.
Nepal pumped hydro project at Tanahu

Nepal pumped hydro project at Tanahu

Engineering firm Lahmeyer International GmbH and sub-consultant Manitoba Hydro International have been awarded a contract by Tanahu Hydropower Ltd. to provide a number of services associated with the development of the 140-MW Tanahu pumped-storage project in Nepal.

Possibilities in centuries old mine in Adirondacks, New York

Possibilities in centuries old mine in Adirondacks, New York

In this Dec. 8, 2016 photo, Steve Burke and Jim Besha of Albany Engineering Corp. stand at the site of an abandoned iron mine in the Adirondacks, in Mineville, N.Y., where they’re seeking a federal permit to build an underground hydroelectric pumped storage project. The hills behind them are “tailings” leftover from crushing ore to extract iron from the mine that closed in 1971. (AP Photo/Mary Esch)
For more information read the full story at Penn Energy